From wolbers@fnal.gov Fri Mar 12 17:16:21 1999 Date: Thu, 14 Jan 1999 08:38:14 -0600 From: Stephen Wolbers To: gpyeh@fnal.gov, paoti@fnal.gov, pyeh@fnal.gov, chenyc@fnal.gov, tony@fnal.gov, antos@fnal.gov, strizene@ns.saske.sk Subject: Farms Schedule for 1999 Hello, We have been asked to present a 1999 farms schedule at the next Wednesday (January 20) CDF offline meeting. We have also been asked to present a request for hardware availability for farms nodes, I/O, disk, etc. by the farms group by January 29. These two are tightly related, so it is a good time to look at both and make our best estimates. I came up with two lists, but it might turn into 1 or maybe 3 depending on the best way to organize it. The first list is a list of milestones. We will have to add beginning and end time for tasks along with this but this is just a first draft! Please send me your comments and suggestions. The dates we are trying to match are this summer's integration milestone, the availability of tape I/O from the data handling group, the mock data challenge in October, the possible second mock data challenge early in 2000, and the collisions in April, 2000. Steve Milestones and Tasks for the CDF farms Stephen Wolbers January 14, 1999 Version 1.0 Milestones 1. Executable running on the farms -- November, 1998 (done) 2. Multiple executables using FBS -- December, 1998 (done) 3. Multiple executables and file I/O -- January/Feb 1999 to/from I/O node 4. Full Prototype test (using all 14 -- February, 1999 nodes) 5. Acquire an I/O node -- May, 1999 6. Tape I/O -- July, 1999 7. Full prototype test w/Tape I/O -- August, 1999 8. Mock Data Challenge 1 -- October, 1999 9. Worker node acquisition -- September, 1999 (50-75 duals) 10. Full farm test, all workers+I/O -- January, 2000 11. Mock Data Challenge 2 -- February, 2000 12. Ready for collisions -- April, 2000 My second list is a list of things that have to be done by us to get ready for use of the farms. Tasks 1. Farm Control (this is the loop that -- now through April, 1999 (Yen-Chu has written down) 2. I/O control (moving the files back and -- now through Oct,1999 forth from tape and I/O to worker nodes) 3. Output control (concatenation, etc.) -- April through Dec,1999 4. cdf catalog access -- Feb through June, 1999 5. Calibration access -- Not known yet