CDF Farms


Project Start Date: Thu 10/1/98
Project Finish Date: Fri 12/29/00

Tasks

IDTask NameDurationStartFinishResource Names% Complete
1
CDF Farms
587 daysThu 10/1/98Fri 12/29/00 0%
2
Prototype Farm Work
305 daysThu 10/1/98Wed 12/1/99 60%
3
Run Executable on Prototype
0 daysMon 11/2/98Mon 11/2/98Tony Chan100%
4
Multiple executables on prototype
31 daysTue 11/3/98Tue 12/15/98Tony Chan100%
5
Full Prototype Farm Test
5 daysMon 2/22/99Fri 2/26/99Tony Chan100%
6
Specify worker nodes
0 daysMon 3/15/99Mon 3/15/99Stephen Wolbers[10%],Tony Chan[10%],Yen-Chu Chen[10%]100%
7
Specify I/O node 1
0 daysMon 5/3/99Mon 5/3/99Stephen Wolbers[10%],Tony Chan[10%],Ping Yeh[10%]80%
8
Acquire I/O node 1
0 daysMon 8/16/99Mon 8/16/99 0%
9
Worker Node Acquisition 1
0 daysThu 9/30/99Thu 9/30/99 0%
10
Integrate new nodes 1
44 daysThu 9/30/99Tue 11/30/99 0%
11
Start using new nodes 1
0 daysWed 12/1/99Wed 12/1/99 0%
12
Use new nodes 1
66 daysWed 12/1/99Wed 3/1/00 0%
13
Worker Node Acquisition 2
0 daysWed 3/1/00Wed 3/1/00 0%
14
Integrate new nodes 2
44 daysTue 2/29/00Fri 4/28/00 0%
15
Start using new nodes 2
0 daysMon 5/1/00Mon 5/1/00 0%
16
Use new nodes 2
175 daysMon 5/1/00Fri 12/29/00 0%
17
Monte Carlo production
360 daysMon 8/16/99Fri 12/29/00 0%
18
Mock Data Challenge 1
23 daysThu 10/14/99Mon 11/15/99 0%
19
Mock Data Challenge 2
22 daysTue 2/15/00Wed 3/15/00 0%
20
Run 2 begins
0 daysSat 4/15/00Sat 4/15/00 0%
21
CDF Farms Software
245.79 daysMon 4/26/99Mon 4/3/00 0%
22
Design software structure
15.79 daysMon 4/26/99Mon 5/17/99Stephen Wolbers[5%],Ping Yeh[50%],Tony Chan[25%],Yen-Chu Chen[25%],Paoti Chang[50%]100%
23
Coordinator
231 daysMon 5/17/99Mon 4/3/00 0%
24
Coordinator Design
22 daysMon 5/17/99Tue 6/15/99 0%
25
V1 Coordinator
22 daysWed 6/16/99Thu 7/15/99 0%
26
V2 Coordinator
143 daysFri 7/16/99Tue 2/1/00 0%
27
V3 Coordinator
44 daysWed 2/2/00Mon 4/3/00 0%
28
Dispatcher
231 daysMon 5/17/99Mon 4/3/00 0%
29
Dispatcher Design
22 daysMon 5/17/99Tue 6/15/99 0%
30
V1 Dispatcher
22 daysWed 6/16/99Thu 7/15/99 0%
31
V2 Dispatcher
143 daysFri 7/16/99Tue 2/1/00 0%
32
V3 Dispatcher
44 daysWed 2/2/00Mon 4/3/00 0%
33
Reconstructor
231 daysMon 5/17/99Mon 4/3/00 0%
34
Reconstructor Design
22 daysMon 5/17/99Tue 6/15/99 0%
35
V1 Reconstructor
22 daysWed 6/16/99Thu 7/15/99 0%
36
V2 Reconstructor
143 daysFri 7/16/99Tue 2/1/00 0%
37
V3 Reconstructor
44 daysWed 2/2/00Mon 4/3/00 0%
38
Collector
231 daysMon 5/17/99Mon 4/3/00 0%
39
Collector Design
22 daysMon 5/17/99Tue 6/15/99 0%
40
V1 Collector
22 daysWed 6/16/99Thu 7/15/99 0%
41
V2 Collector
143 daysFri 7/16/99Tue 2/1/00 0%
42
V3 Collector
44 daysWed 2/2/00Mon 4/3/00 0%
43
Splitter
231 daysMon 5/17/99Mon 4/3/00 0%
44
Splitter Design
56 daysMon 5/17/99Mon 8/2/99 0%
45
V1 Splitter
22 daysTue 8/3/99Wed 9/1/99 0%
46
V2 Splitter
109 daysThu 9/2/99Tue 2/1/00 0%
47
V3 Splitter
44 daysWed 2/2/00Mon 4/3/00 0%
48
Spooler
231 daysMon 5/17/99Mon 4/3/00 0%
49
Spooler Design
56 daysMon 5/17/99Mon 8/2/99 0%
50
V1 Spooler
22 daysTue 8/3/99Wed 9/1/99 0%
51
V2 Spooler
109 daysThu 9/2/99Tue 2/1/00 0%
52
V3 Spooler
44 daysWed 2/2/00Mon 4/3/00 0%
53
Exporter
231 daysMon 5/17/99Mon 4/3/00 0%
54
Exporter Design
56 daysMon 5/17/99Mon 8/2/99 0%
55
V1 Exporter
22 daysTue 8/3/99Wed 9/1/99 0%
56
V2 Exporter
109 daysThu 9/2/99Tue 2/1/00 0%
57
V3 Exporter
44 daysWed 2/2/00Mon 4/3/00 0%
58
Database Retriever
231 daysMon 5/17/99Mon 4/3/00 0%
59
Database Retriever Design
56 daysMon 5/17/99Mon 8/2/99 0%
60
V1 Database Retriever
22 daysTue 8/3/99Wed 9/1/99 0%
61
V2 Database Retriever
109 daysThu 9/2/99Tue 2/1/00 0%
62
V3 Database Retriever
44 daysWed 2/2/00Mon 4/3/00 0%
63
Disk Manager
231 daysMon 5/17/99Mon 4/3/00 0%
64
Disk Manager Design
56 daysMon 5/17/99Mon 8/2/99 0%
65
V1 Disk Manager
22 daysTue 8/3/99Wed 9/1/99 0%
66
V2 Disk Manager
109 daysThu 9/2/99Tue 2/1/00 0%
67
V3 Disk Manager
44 daysWed 2/2/00Mon 4/3/00 0%
68
Tape Manager
231 daysMon 5/17/99Mon 4/3/00 0%
69
Tape Manager Design
56 daysMon 5/17/99Mon 8/2/99 0%
70
V1 Tape Manager
22 daysTue 8/3/99Wed 9/1/99 0%
71
V2 Tape Manager
109 daysThu 9/2/99Tue 2/1/00 0%
72
V3 Tape Manager
44 daysWed 2/2/00Mon 4/3/00 0%
73
Worker Node Manager
231 daysMon 5/17/99Mon 4/3/00 0%
74
Worker Node Manager Design
56 daysMon 5/17/99Mon 8/2/99 0%
75
V1 Worker Node Manager
22 daysTue 8/3/99Wed 9/1/99 0%
76
V2 Worker Node Manager
109 daysThu 9/2/99Tue 2/1/00 0%
77
V3 Worker Node Manager
44 daysWed 2/2/00Mon 4/3/00 0%
78
Bookkeeper
231 daysMon 5/17/99Mon 4/3/00 0%
79
Bookkeeper Design
22 daysMon 5/17/99Tue 6/15/99 0%
80
V1 Bookkeeper
22 daysWed 6/16/99Thu 7/15/99 0%
81
V2 Bookkeeper
143 daysFri 7/16/99Tue 2/1/00 0%
82
V3 Bookkeeper
44 daysWed 2/2/00Mon 4/3/00 0%
83
Messenger
231 daysMon 5/17/99Mon 4/3/00 0%
84
Messenger Design
56 daysMon 5/17/99Mon 8/2/99 0%
85
V1 Messenger
22 daysTue 8/3/99Wed 9/1/99 0%
86
V2 Messenger
109 daysThu 9/2/99Tue 2/1/00 0%
87
V3 Messenger
44 daysWed 2/2/00Mon 4/3/00 0%
88
DB Server Interface
231 daysMon 5/17/99Mon 4/3/00 0%
89
DB Server Interface Design
56 daysMon 5/17/99Mon 8/2/99 0%
90
V1 DB Server Interface
22 daysTue 8/3/99Wed 9/1/99 0%
91
V2 DB Server Interface
109 daysThu 9/2/99Tue 2/1/00 0%
92
V3 DB Server Interface
44 daysWed 2/2/00Mon 4/3/00 0%
93
PM Interface
231 daysMon 5/17/99Mon 4/3/00 0%
94
PM Interface Design
56 daysMon 5/17/99Mon 8/2/99 0%
95
V1 PM Interface
22 daysTue 8/3/99Wed 9/1/99 0%
96
V2 PM Interface
109 daysThu 9/2/99Tue 2/1/00 0%
97
V3 PM Interface
44 daysWed 2/2/00Mon 4/3/00 0%
98
Operator Interface
231 daysMon 5/17/99Mon 4/3/00 0%
99
Operator Interface Design
56 daysMon 5/17/99Mon 8/2/99 0%
100
V1 Operator Interface
22 daysTue 8/3/99Wed 9/1/99 0%
101
V2 Operator Interface
109 daysThu 9/2/99Tue 2/1/00 0%
102
V3 Operator Interface
44 daysWed 2/2/00Mon 4/3/00 0%
103
Catalog Interface
231 daysMon 5/17/99Mon 4/3/00 0%
104
Catalog Interface Design
22 daysMon 5/17/99Tue 6/15/99 0%
105
V1 Catalog Interface
22 daysWed 6/16/99Thu 7/15/99 0%
106
V2 Catalog Interface
143 daysFri 7/16/99Tue 2/1/00 0%
107
V3 Catalog Interface
44 daysWed 2/2/00Mon 4/3/00 0%

Resources

IDNameGroupMax UnitsPeak Units
1Stephen Wolbers 20%5%
2Ping Yeh 50%50%
3Tony Chan 100%100%
4Yen-Chu Chen 50%25%
5GP Yeh 10%0%
6Miroslav 100%0%
7Paoti Chang 50%50%
8Antos 100%0%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete
3Run Executable on PrototypeTony Chan0 hrsMon 11/2/98Mon 11/2/98100%
4Multiple executables on prototypeTony Chan248 hrsTue 11/3/98Tue 12/15/98100%
5Full Prototype Farm TestTony Chan40 hrsMon 2/22/99Fri 2/26/99100%
6Specify worker nodesStephen Wolbers0 hrsMon 3/15/99Mon 3/15/99100%
6Specify worker nodesTony Chan0 hrsMon 3/15/99Mon 3/15/99100%
6Specify worker nodesYen-Chu Chen0 hrsMon 3/15/99Mon 3/15/99100%
7Specify I/O node 1Stephen Wolbers0 hrsMon 5/3/99Mon 5/3/990%
7Specify I/O node 1Tony Chan0 hrsMon 5/3/99Mon 5/3/990%
7Specify I/O node 1Ping Yeh0 hrsMon 5/3/99Mon 5/3/990%
22Design software structureStephen Wolbers3.16 hrsThu 5/6/99Mon 5/17/99100%
22Design software structurePing Yeh7.9 hrsFri 5/14/99Mon 5/17/99100%
22Design software structureTony Chan15.79 hrsThu 5/6/99Mon 5/17/99100%
22Design software structureYen-Chu Chen31.58 hrsMon 4/26/99Mon 5/17/99100%
22Design software structurePaoti Chang63.17 hrsMon 4/26/99Mon 5/17/99100%