NEWS:
An access to collision hall was scheduled to remove a broken wire in COT.
SVX is down since the incident when beam destroyed several ladders. Beam
division is waiting for new RF's to increase luminosity. This will increase
luminosity by factor of 2 to 4 by increasing antiprotons. This will cost
about 2 weeks to install them. Also they are thinking about to shield the
low beta quads to reduce beam loss.
SYSTEM:
Mark said Rich Schmitt is thinking about updating iFIX software to version
2.5 since D0 is running verion 2.5. Steve will look into this issue.
PLUG HV:
Luciana needs to create iFix tags for Oracle database. Margherita will contact
her.
CLC:
We need to send CLC status signal to ACNET for accelerator people. We are
still debating how to proceed.
VNODE1:
The vnode1 hung again during the virus scans. Twice since the last meeting
we had 2 weeks ago.
ICICLE:
The Icicle excutable is crashing regular bases. The error has to do with
lack of virtual memory. Mark will look into the problem.
SVX:
Andy said that SVXIICON disk was full and could not open any pictures. However
there seems 150Mbyte available. Steve suggested that he should delete all
the pictures in the disk and download from the picture server to save more
space. The trigger inhibits for L00, SVX, and ISL are working fine now.
GAMMA:
Steve said he is cosidering switching to APACS readout. It would cost about
1 week.
PSM:
Since the PSM instruction to shift crew is not updated, there was some
confusion in how to unmask channels. Marcin promised to update the
instruction.