Monitoring Controls System meeting on October 28, 2003


Attendance:
Mary Convery, Steve Hahn, Dan Ryan, Yeongdae Shon, Margherita Vittone, John Yoh, JC Yun

NEWS:
We will have a new batches of ACEs soon. Since the old crews has limited experience with beams(ony ~5 days), their beam experiences may not be passed on to the new ACEs very smoothly. We need to have good instructions for this.

  • Steve's transparacies on the shutdown progress.
  • PisaBox:
    Irina is having trouble in making a new excutable for the Xenon flasher calibration in MUON3. An header file called wchar.h gives errors. Margherita said she had similar experience while working with the EDA tool kit. She said she will help Irina.

    MUON3:
    Argonned people are pressing for the HV feedback system for the central calorimeter chambers. Yeongdae said once he watched Randy fixing the problem a couple of years ago. However the source code was not saved somehow. He promised to work on it this week.

    PSM:
    Dan said he noticed something wrong with the iFix database. All the variables in the data base is reading -2. Steve thought it might related to the Firmware download to the Cryo computers.

    CLC:
    Mary wants to upgrade the CLC computer. Since we have only 3 weeks left for this shutdown, we need to start as soon as possible.