Rough Schedule for next 6 weeks =============================== Feb 2 - Feb 8 -------------- 1. Jim continues to work on laying out the PCP this week, and should have a design by next week 2. Steve will work with Matt in procuring all the parts and seeing if Craig Drennan can work on an assembly diagram for assembling these cables. Feb 9-Feb 18 ------------ 3. After Jim is finished with the PCP layout, he will work on designing an adaptor which mates the new PCP to the Test Junction card (used for port card testing). 4. In parallel, Jim get's quotes for constructing the PCP Feb 19 - Mar 2 -------------- 5. PCP assigned to a vendor and board is constructed 6. As soon as Jim can, he sends the junction card adaptor out for fabrication (can we use the same vendor?) 7. 20 Cable sets assembled Mar 3 - Mar 15 -------------- 8. Assemble a few prototype PCP's are made here, rest are shipped out for assembly (Subsem?) 9. Assemble junction board adaptors here or outside? ============================================================== ** PCP == Port Card Pigtail