CLC Milestones Towards the Commissioning Run (May 1st - July 31st)
GOALS:
- CLC Installation:
complete East by mid-June
- West is installed and cabled: needs final LED
- LED Calib. System: finalize LED choice end of May
- Install and cable up East CLC after that
- Alignment: finalize by mid-July
- Gas System: finalize by mid-June (so we can exercise it)
-
-
- High Voltage:
Basic multi-chann operationality by mid-May
- All modules in hand and cabled up
- Can set voltages (a) by hand, (b) by RS-232 (c) through Plug program
- Need Bologna group to incorporate CLC to plug daisy chain + program,
by end-June.
- Need FIX pages (by when? - for Run 2)
-
-
- F.E. Electronics:
Fully commissioned by mid-July
- Front-end hardware: Need CLC transition boards - mid May
- Full F.E. readout by end of May
- Full amplitude calibrations by end of June
- Full time calibrations by mid-July
-
-
- Standalone DAQ:
Losses to Tev. by beg. of June
- Xilinx code operational - end of May
- Dual Port Memory readout - mid-May
- Scaler readout - end of May
- Online Lum. code - version 1.0 - mid-May
- Tevatron communications - mid-May
- 6U to 9U smart sockets - mid-June
-
-
- DAQ:
Full CLC readout mid-July
- CLC integrated to DAQ - beg. May
- E-banks by mid-June
-
-
- Consumers/Monitors:
v1.0 ready mid-july
- Acnet
- Lummon
- Ymon
- CAL_CLC
- Evt. Display
- HV "FIX"
Jacobo Konigsberg