Luminosity group "to do list"
---------------------------------------------------------------------

(1) Documentation
===============

>>> CDF notes:

 * NIM Article from Pisa 2000, Elba (Jaco) - done
* PMT measurements with the solenoid (Ming/Jaco) (+add commissioning data) - done
* Calibration system (Alexei+) - started
* Online DAQ (Sergey/Jaco/Dmitri) - january version under revision
* Geant simulation (Dmitri/Darin) - done
 * Alignment (Mayling+) - done
 * Mechanical construction (Mayling+) - started
 * Gas system (Mayling) - under revision
 * Trigger note - not started

* Commissioning run:
   > CLC performance note - started
   > Luminosity measurements -  started
       >>> NIM paper with commissioning run performance (Jaco+) - not started

 * Propaganda plots + posters  (Jaco)  - started
 

(2) Calibrations (Alexei --> Alexander)
===========

* We need to establish a routine to understand the stability and the
precision of the system. We need to all be able to run and look
at calibration results in a very easy manner. This includes
pedestals, qie, gains, timing. - in progress

* We need to propagate the calibration results into the databases
and into the offline reconstruction programs (D to E etc.)
    > Amplitude calibrations - in progress
    > Time calibrationsnot started

* We need to re-establish HV and Pressure operation points - started
  together with Xilinx &  discriminator thresholds

* Even out the light from LEDs in east/west - started

* "Standalone" calibration consumer - started

(3) Gas system (Mayling)
  ===========

* Fix all leaks -done
* Fill with N2 and exercise computer controls as if in real run - done
* Pressure control by computer? needs revision - started
 

(4) Electronics
===========

* Find and fix all bad channels (Alexei/Ming) - in progress
* Re-cable the crate (Jaco/Dmtri) - done
* Implement the Xilinx particle counting (Dmitri/Jaco) -not started
* Make timing diagrams for every path we have (Ming w/Alexei) - in progress
* Implement amplitude gates - not started
* Fix signal connectors - not started
 

(5) Afterpulses
===========

* Understand the effect on the data (Sergey/Ming)  - started
* Possible solutions if needed
 

(6) Trigger (Alik/Darin/Dmitri)
=======

* Fix to avoid shorts in the future  - not started
* Test spare - not started
* Understand trigger efficiency - in progress
 

(7) Gating (Gator) board (Andrei/Alik/Jaco/Dmitri)
====================

* Need specs - done
* Need $ - done
* Need schedule + people - in progress
 

(8) Online DAQ (Dmitri+)
==========

* Understand if timing is needed online for Lum corrections - not started
* Implement 6U TDC for corrections(?) and Z position - not started
* Solve issues of speed in the program - started
* Solve issues of accuracy (16 -> 32 bits) - started
* Add uncertainties to the calculations - started
* Add GLIVE to the integrated luminosities - done
* Decide on estimators - started
* Estimate correction for losses - started
 

(9) Offline Luminosity Reconstruction + validation (Ming/Sergey/Dmitri/Jaco)
======================================

+ Finalize code to reconstruct Luminosity - started
    > includes offline calibrations (spp + T0's)
    > includes widths vs start, time vs amplitude
+ Finalize code to write to database the results offline+online - not started
+ Start W studies - not started
+ Think about automatization of it all - not started
+ Validation code in production - not started
+ Luminosity uncertainties - not started
+ Time clusters... - not started
 

(10) Simulations (Dima+)

 * Add all possible materials
 * Make data and MC match
 * Make program user friendly for syst. studies (easy inputs and outputs)
 

(11) Alignment (Mayling)
===========

+ Find CLC position relative to plug
(include rotation, z, angle) - done
+ Find plug position relative to beam-line - done

(12) High Voltage
 ==============

+ IFIX needs to be implemented (Andrea Bocci) - started
+ Need to set current limits on CAEN (Jaco) - Not started
 

(13) LUMMON/YMON /Evt Display (Ming/Jaco)
==========================

+ Do we need YMON - ? prob. not
+ Mods to LUMMON - done
+ Mods to Evt Display - ?
 

(14) Miscellaneous
===============

+ TLD + mylar installation
+ CLC rotation