Run Plan
Scheduled running time in July (7 days total):
- From wednesday July 2nd 8:00 am to 12:00 noon on thursday July 3rd (28 hrs)
- From thursday July 17th 6:00 pm to saturday July 19th 6:00 pm (48 hrs)
- From friday July 25th 8:00 am to sunday July 27th 8:00 am (48 hrs)
- From wednesday July 30th 8:00 am to friday August 1st 8:00 am (48 hrs)
Tasks at the testbeam for July/August (in order!!!!):
- Goal: Improve N_zero with std. configuration.
- Bring clean bench to testbeam counting room (JK)
- Make new end-caps (fix LED) (JK)
- Make small cap for cone (JK)
- Make new clean 2 mil aluminized mylar cone (SK/AN)
- Make new clean 5 mil thick Aluminized mylar cone (SK/AN)
- Make cone to PMT connection (SK/JK)
- Make single cable delays (AN/Derwin)
- Add LeCroy TDC to readout (AN/KB)
- Put mount together and re-align (DN/ALL)
- Make sure timing is as before
- Do N2 run / then Vacuum run / then Isobutane @ 6.5 psi run
-
- Goal: Improve timing measurements.
- ACD resolution and active vs passive divider:
- Change to passive divider
- Keep linear discriminator
- re-do single p.e calib
- one standard Iso @ 6.5 psi run
- Change ADC slope from 0.4 pC/count ---> 0.05 pC/count
- re-do single p.e. calib
- Standard run
- Discriminator:
- Tune CFD --> various runs?
- Noise in the system...
-
- Goal: Measure UV fraction of light
- Open and close cone, use different filters and std. run
-
- Goal: Test new PMT's
- First test XP2020Q with:
- Gain of 10**6 instead of 10**7
- + same collector as for 29mm PMT's
- Do single p.e. calib
- Do run with LED at fixed amplitude A_o
- Standard run
- Pressure scan to test geometry(?)
- Prototype of middle layer of CLC's
- Use Phillips 29mm PMT + collector
- Single p.e calib (?) not likely
- Do LED run with A_o amplitude to calibrate single p.e.
- Do standard run
- Repeat for Hamamatsu 29mm
- Repeat for Hamamatsu 25mm
- Prototype of outer layer of CLC's
- Use best of Hamamatsu 25mm or 29mm + collector
- Single p.e calib (?) not likely
- Do LED run with A_o amplitude to calibrate single p.e.
- Do standard run
-
- Prototype of inner layer of CLC's
- Use Hamamatsu 19mm and/or 25mm + collector
- Single p.e calib (?) not likely
- Do LED run with A_o amplitude to calibrate single p.e.
- Do standard run
-
-
- Goal: Test angular dependance
- Goal: Test tranparent cone
- Replace aluminized cone by transparent cone
- Standard run
- Angles
- Goal: Cerenkov threshold scan
Plots to make and results to show:
- Window deconvolutions plots
- N_zero
- Ampl mean vs pressure
- Sigma_ampl vs # p.e.
- Amplitude for all gases tested
- Sigma_time vs. # p.e.
- ....
Jacobo Konigsberg